October 8, 2026
A resident who spoke to the Neosho City Council on Aug. 4 described the wooded stretch by the bridge as heavily wooded and cooler than other parts of the walking path.
The resident was the first of five people who signed up to speak about the Morse Park trail bridge that night, and wanted it rebuilt. Two weeks later, the council approved a different piece of the fix. It's a sidewalk that starts at the Lampo Building and goes around Hatchery Branch. Separately, the city has been putting in trail lighting phase by phase, and bids for the last phase were due Oct. 1. That lighting also ends at the Lampo Building.
So both projects now lead to the same corner of the park. Here's how that came about, and what's still undecided.
The public record on this is short, and every step is dated.
That's about ten weeks from washout to an approved bid. The sidewalk came first, and so far the record says nothing about what happens to the bridge itself.
The sidewalk is a small project. The city's bid packet asks for 280 feet of ADA-compliant sidewalk, 10 feet wide. It connects to the existing trail and to the pavilion and playground area at 563 E. Spring St. The city describes the Morse Park nature trail as 1.73 miles long, so the new piece is roughly 3% of that length.
What matters most is where it connects. The Neosho Daily News reported that the new sidewalk will run from the Lampo Building sidewalk to the paved walking trail, "providing a continuous route to the existing trail system." The city's lighting announcement places the Lampo Building at the corner of La-Z-Boy Parkway and E. Spring Street. The Phase 4 lighting bid packet lists its address as 500 E Spring Street.
Hatchery Branch used to be crossed out among the trees. The planned route goes around it instead, starting at a building on a main road. A 10-foot-wide sidewalk that meets ADA standards suits wheelchairs, strollers, and people walking side by side, and it runs past a playground and a pavilion. It will be a different walk from the wooded stretch the resident described.
The trail lighting project was already underway before the flood. On Jan. 20, 2026, the city announced a four-phase plan to light the trail from the north fishing dock to the Lampo Building. At that point, Phase 1 was under construction and close to finished.
The project has moved faster than first planned. At its Feb. 17 meeting, the council approved going ahead with Phase 2 at the original contractor's prices, which put the work a year ahead of schedule. Earlier, at the Oct. 21, 2025 meeting, Henson Electric received a $24,600 award for new LED lights along the paved trail. The report doesn't say which phase that covered.
Phase 4 is the current step. The city asked for sealed bids on 12 LED lights and posts, plus reconnecting wire to damaged trail lights. Bids were due at City Hall, 203 East Main Street, on Thursday, Oct. 1, 2026, at 2 p.m. The mandatory pre-bid meeting on Sept. 16 was held at the Lampo Building.
So the lights started at the north end by the fishing dock and are working south toward the Lampo Building, the same corner where the new sidewalk begins. Once both are finished, the south end of the trail will have lighting plus a wide, paved link from a main-road building to the loop. As the days get shorter this fall, the lit section of the trail is the part people can still use after work.
Approving a route around the creek doesn't settle what happens at the creek. Here's what the public record leaves open as of early October:
The resident's point still applies while those questions are open. A route around the creek doesn't bring back the cool, wooded stretch described along the water. The city's sidewalk decision doesn't rule out a new crossing later, and it doesn't promise one.
The fastest way to get updates is the City of Neosho Facebook page, where the city posted the original washout notice. For anything more specific, the Phase 4 bid packet lists Kenny Balls, Parks Director, at 417-451-8005, 215 Wheeler St. The city's bid page for the Morse Park Sidewalk shows the dates for that project.
The bridge was one crossing in a big park. The city puts Morse Park at nearly 400 acres along Hickory Creek. It also mentions an ongoing extension of the paved trail toward the Neosho National Fish Hatchery. That extension makes the south end even more important. Whatever happens at Hatchery Branch will shape how the trail eventually connects to the hatchery.
Here's what the city lists away from the washout:
Lampo Pavilion 1 is the only name on that list tied to the flood. It's where the trail washed out, it's near the corner where the new sidewalk begins, and it's at the south end where the lighting finishes. Watch the city's next update on that corner, whether it's a contractor's start date, the Phase 4 award, or a decision on the crossing, to see what the south end of Morse Park will look like next year.
If you own a home near Morse Park or anywhere else in Newton County and want to know what nearby park work might mean for its value, Susan D Goodall and the Legacy Real Estate team are glad to talk it over with you. Start with a free home valuation, and we'll give you a straight answer based on what's actually happening in your part of town.