November 12, 2026
When was the last time you drove from Southwest City to Anderson without thinking about the route first? For most of 2026, that drive meant planning ahead. So did the short trip on Route H south of Pineville.
As of this week, both routes are open again. The Missouri Route 43 bridge over the Elk River reopened at 3:30 p.m. on Wednesday, Oct. 14, according to MoDOT's traffic alert. The Route H bridge over Goodin Hollow Creek followed at 10 a.m. on Friday, Nov. 6, about a month ahead of its contract deadline. The next big round of state road work in McDonald County won't be on the back roads, though. MoDOT's construction schedule puts it on Interstate 49. That's the highway that carried the Route H detour, and it's scheduled for work at Anderson, Pineville and the stretch north of Goodman.
These were two bridges of about the same age, carrying about the same traffic, replaced a few months apart. MoDOT described both of the old structures the same way: deteriorating and in need of frequent maintenance.
| Route 43 over Elk River | Route H over Goodin Hollow Creek | |
|---|---|---|
| Location | Near Cowskin Conservation Area, west of Anderson | Near Pineville, between I-49 and Business 71 |
| Original bridge built | 1960 | 1963 |
| Daily traffic | About 1,500 vehicles | About 1,360 vehicles |
| Closed | Week of May 4 | Week of July 27 |
| Reopened | Oct. 14, 3:30 p.m. | Nov. 6, 10 a.m. |
| New bridge | 31 ft longer, 6 ft wider, slightly higher | 10 ft longer, 4 ft wider |
| Contractor | West Plains Bridge & Grading LLC | Hartman & Company Inc. |
| Project cost | $5.1 million | $1.6 million |
Together, the two crossings carried close to 2,900 vehicles a day. Neither one was closed for long by highway-project standards. But each sits on a route where the alternative is a lot longer than the bridge itself.
The Route 43 closure lasted longest because the project started twice. Crews began in February. The work was put on hold in March over what MoDOT called "supply issues," then picked back up the week of May 4, the McDonald County Press reported. MoDOT allowed up to 160 days for the closure. Through traffic was sent on a signed detour using Routes 76, 59 and 90.
For Southwest City, that detour mattered more than the bridge's location suggests. The McDonald County Press noted that the closure pushed commuters and McDonald County High School students onto one route toward Anderson and the northern part of the county. In the paper's words, it was "the twistier of two options." The school district planned to send Southwest City bus Route #41 through Grove, Oklahoma, instead. Superintendent Eric Findley said in a statement that the change would add about 13 miles and roughly 20 minutes per trip for 16 students. "This project will make travel safer for everyone, including the buses that transport our students each day," he said in the same statement, as quoted by the Press.
The finished bridge is more than a straight swap. Besides the extra length and width, the contractor added object markers at both ends, put down permanent striping and stabilized the Elk River bank near the bridge.
That riverbank matters to anyone who fishes or floats this part of the Elk. MoDOT kept Cowskin Access open through construction. Boats and canoes could still pass under the work zone except during short closures over the channel. The Missouri Department of Conservation lists Cowskin Access at 40.8 acres, with a parking lot and a concrete boat ramp. The species list includes white bass, rock bass, sunfish, suckers, catfish, crappie and black bass. Camping is not allowed there. With the bridge open, the ramp is back on the direct Route 43 drive.
The same contract also covered ditch stabilization on Route 59 near Noel, just north of County Route DD.
The Route H project was smaller and faster. Construction started the week of July 27. The signed detour ran on I-49, McDonald County Route EE and Business 71. MoDOT's project plans named three local roads that had to stay reachable throughout: Canoe Camp Lane, Goodin Hollow Road and Beckett Lane.
Hartman & Company of Springfield had until Dec. 1, 2026, to finish. The bridge opened to traffic on Nov. 6 with new object markers and striping in place. The April Press story had warned that the closure could last up to five months. It came in at a little over three.
This is where the two projects lead into what's next. For three months, I-49 was the bypass for Route H. Now I-49 is the road on MoDOT's list.
MoDOT's 2027–2031 Highway and Bridge Construction Schedule, dated April 14, 2026, lists several I-49 projects in McDonald County. Each one has an anticipated contract award date. That's the point when MoDOT expects to hire a contractor, not a lane-closure date.
The third item brings the season full circle. The Route H bridge MoDOT just finished crosses Goodin Hollow Creek. The I-49 bridge on next spring's list crosses Goodin Hollow Road, which was one of the roads the Route H project had to keep open. Pineville's south side will be on MoDOT's work list two years in a row.
The 2028 column of the same schedule shows three more McDonald County projects. One is an I-49 bridge rehabilitation over Sugar Fork Creek north of Goodman, estimated at $959,000. The others are a rehabilitation of the Route 59 bridge over the Elk River in Noel and a replacement of the Route 90 bridge over Trent Creek. Route 59 and Route 90 were two of the three roads on this year's Route 43 detour.
Over two years, the work moves from the two-lane bridges that pushed traffic onto other roads to the roads that took that traffic.
MoDOT's Southwest District posts closures and reopenings as traffic alerts. Both of this year's reopenings came out that way the same day they happened. The district gives three ways to get updates:
The Route H project page still shows the full run of milestones, from the June 2026 contract award to the Nov. 6 completion.
A bridge closure only shows up on a map for a few months, but it changes the drive to every property on that road for as long as it lasts. At Legacy Real Estate, we keep track of which back roads and bridges reach a piece of land in McDonald County, because that drive matters as much as the acreage. If you're thinking about what your place along Route 43, Route H or the I-49 corridor is worth now that the detours are over, ask us for a free home valuation and we'll give you a straight answer.
Stay up to date on the latest real estate trends.
Backed by local knowledge, strong relationships, and a passion for helping people, our team is committed to delivering a smooth and personalized real estate experience from start to finish.